March 2026

New Transmission Tariffs, Methodology and Interconnection Contract Model in Mexico

Share

Mexico's Comisión Nacional de Energía (CNE) has issued a series of regulations that are reshaping the legal framework for electricity transmission. This note describes the new methodology for calculating transmission tariffs, and the unified model contract for grid interconnection and connection. It also addresses the first set of regulated tariff rates for 2026, published by the Comisión Federal de Electricidad (CFE), the Mexican state utility, based on the new methodology.

New Transmission Tariff Methodology

On 26 November 2025, the CNE published in the Diario Oficial de la Federación (DOF) a new methodology for calculating regulated transmission tariffs. The instrument replaces the previous framework under Acuerdo A/044/2022 and fulfils the mandate imposed by the constitutional reform of 31 October 2024, which reaffirmed the State's exclusive role in electricity transmission and required the CNE to update the tariff regime within 180 business days.

2026 Transmission Tariffs

The CNE has already applied the new methodology and approved the first set of regulated transmission tariffs, effective from 1 January to 31 December 2026. The approved rates are as follows:

Voltage Level Injection ($/kWh) Withdrawal ($/kWh)
≥ 220 kV $0.0607 $0.0791
< 220 kV $0.1100 $0.1801

The figures confirm the structural design of the methodology: withdrawal tariffs are materially higher than injection tariffs, and lower-voltage connections carry a premium over higher-voltage ones.

Unified Interconnection Contract Model

Alongside the tariff framework, the CNE has also overhauled the contractual regime for connecting to the grid. On 17 March 2026, it published a single model contract for interconnection, connection, or both, to the national transmission grid and general distribution networks. This replaces the four resolutions and respective clarifications issued by the now-extinct Comisión Reguladora de Energía (CRE) between 2015 and 2016.

The new model applies to power plants, energy storage systems, and load centres with contracted capacity of 1 MW or more. It consolidates what were previously separate interconnection and connection agreements into a single adaptable model contract. Any modification that alters the terms of the model contract requires prior CNE approval.

Several provisions of the model agreement are worth noting. The model includes a detailed termination regime covering insolvency, regulatory breach, and failure to meet estimated operation dates. Force majeure is carefully defined, it covers natural disasters, government actions, and grid emergencies, but expressly excludes changes in financial condition, currency fluctuations, and late equipment delivery.

The model also provides that disputes must be resolved before the federal Mexican courts of the place where the interconnection or connection point is located. Therefore, foreign investors must continue to consider and if necessary revisit investment corporate structures for their projects in Mexico.