January 04, 2021

IRS Grants Beginning of Construction Relief for Offshore Renewable Projects and Renewable Projects on Federal Land

Share

On December 31, 2020, the US Treasury Department and the Internal Revenue Service (the “IRS”) issued Notice 2021-05 (the “Notice”), which provides relief for offshore renewable energy projects and renewable projects constructed on federal land. Specifically, the Notice allows the Continuity Safe Harbor to be satisfied for projects constructed offshore or on federal land if they are placed into service no more than 10 calendar years after the calendar year during which construction began. This relief is expected to provide additional certainty for taxpayers developing projects offshore or on federal land, given the significant construction delays often associated with such projects. Read about the Notice in this Mayer Brown Legal Update.

Related Services & Industries

Services

Stay Up To Date With Our Insights

See how we use a multidisciplinary, integrated approach to meet our clients' needs.
Subscribe